FOI Request - School Building Information
Request 101003359664
1. The total number of new schools currently planned to be built.
2. The total number of schools built from 2017 to current year.
3. The total number schools that have been identified containing asbestos from 2015 to current year
4. The total overspend costs on building new schools and nursery buildings
5. The total number of schools that have been substantially refurbished from 2016/17 to current year.
6. The total number of schools in good or satisfactory condition from 2016/17 to current year.
7. The current total number of schools in good or satisfactory condition.
8. The current total number of schools in poor or bad condition.
9. The total number of school buildings that currently pose a risk to life.
10. The total cost of using external designers for school building projects from 2016/17 to current year.
11. The total proportion of school buildings that are believed to be past their estimated initial design life, which could be extended adequate maintenance
12. The total number of pupils number of pupils that are learning in a school that requires major rebuilding or refurbishment.
13. The total number of schools in the most urgent need that are due to have major rebuilding or refurbishment
14. a) The total amount of school which its PFI or equivalent contract are coming to an end.
b) A total number of schools that are under PFI or equivalent contract.
15. The total number of schools that have a dedicated car park. A total breakdown of the number of car park spaces.
Response 09-08-2023
1. Zero
2. 3
3. 47
4. £388,000
5. 4
6. This information is available on the Scottish Government website and is therefore exempt under section 25 of the Freedom of Information (Scotland) Act 2002, information otherwise accessible. For ease of reference please find a link to the web page here: https://www.gov.scot/publications/school-estates-statistics/
7. 25
8. 29
9. 0
10. £4,980,090
11. Our surveys are general condition surveys and do not consider buildings against initial design life.
12. 5,426
13. The Moray Learning Estate Strategy identifies current school new build and refurbishment plan and is published on the council website. This information is therefore exempt under section 25 of the Freedom of Information (Scotland) Act 2002, information otherwise accessible. For ease of reference please find a link to the web page here: http://www.moray.gov.uk/downloads/file149062.pdf
14. a) Zero. b) 3.
15. 41. Please see details below:
Secondary:
Buckie Elgin Academy Elgin High Forres Keith Grammar Lossiemouth Milne's High Speyside |
49 161 84 84 40 97 85 60 |
Primary:
Aberlour Bishopmill Cluny Cullen Dallas Dyke East End Findochty Glenlivet Greenwards Hopeman Hythehill Keith Primary Kinloss Knockando Lhanbryde Linkwood Millbank Milne's Primary Mortlach Mosstodloch Mosstowie New Elgin Newmill Pilmuir Portessie Portknockie Rothes Seafield St Gerardine St Sylvester's St Thomas West End |
13 35 15 24 6 10 30 15 8 30 10 35 69 30 10 28 47 48 20 20 20 14 46 10 31 15 10 20 37 46 10 5 27 |