FOI Request - EV Chargers

Request 101002595197

1. How many EV charging points have you installed in your authority area since 2017? (Please give data broken down by calendar year)

2. How many EV charging points that are currently installed in your authority area are either a) rapid 43kW+, b) fast 7kW – 42kW or c) slow 3-6kW? (Please give data separately, as of today’s date)

3. How many EV charging points do you plan to install in your authority area between today’s date and 31st December 2025 that are either a) rapid 43kW+, b) fast 7kW – 42kW or c) slow 3-6kW? (Please give data separately broken down by calendar year – if 2025 is too far away, please give details on as much forecast as you have)

4. How many requests lobbying for on-street EV charging points have you received since 2017? (Please give data broken down by calendar year)

Please prioritise your response to the questions in the order asked i.e. if time constraints do not allow for all questions to be answered, please answer Q1 first.
 

Response 14-10-2020

1. 3

2. All 2018 - 2 x Rapid, 1 x Fast

3. All chargers are grant funded by Transport Scotland on a year by year basis. Currently we have a grant that needs to be used by March 2021, with no guarantee of funding past that date.

Site installations are currently in progress for the following :-

3 x Rapid, 4 x Fast

4. Only 1 enquiry has been received for on-street EV Charging Points