FOI Request - Cycling Infrastructure

Request 101002409574

1) Please provide information on how much has been spent on cycling infrastructure in the area you're responsible for, broken down each year for the last 5 available financial years.

Where cycling provision has been provided as part of wider improvement works, these should be listed as cost for the cycling-related improvements, not for the entire project.

2) Please also list the amount spent, sorted by Funding Type/Source (e.g. Capital, Section 106, Central Government funding initiatives), broken down each year for the last 5 available financial years.

3) Please detail how much has been spent, broken down by year, on dedicated segregated cycling infrastructure (only dedicated cycle paths featuring light, full or kerb segregation away from motor vehicles, NOT included on-road painted cycle lanes, shared usage paths or existing re-purposed shared usage infrastructure such as canal towpaths or greenways).

For the avoidance of doubt, segregation refers to the physical separation of cyclists from motorised traffic, and can be provided by the following:
Kerbs
Kerbed plinths AKA Armadillos
Bollards
Soft margins or verges
Crash barriers (Trunk roads)

4) Please detail how many miles of segregated infrastructure has been built in the last 5 years (only dedicated cycle paths featuring light, full or kerb segregation away from motor vehicles, NOT included on-road painted cycle lanes, shared usage paths or existing re-purposed shared usage infrastructure such as canal towpaths or greenways).

For the avoidance of doubt, segregation refers to the physical separation of cyclists from motorised traffic, and can be provided by the following:
Kerbs
Kerbed plinths AKA Armadillos
Bollards
Soft margins or verges
Crash barriers (Trunk roads)

Response 13-03-2020

1. and 2. 

2015/16

Cycling Walking Safer Streets (Transport Scotland Grant Fund) - Sanqhuar Road and Roysvale Park Forres, Shared Path - £74,445.19

2016/17

Cycling Walking Safer Streets (Transport Scotland Grant Fund) – Balvenie St Dufftown, Footway Redetermination to cycle track - £1,341.97 Community Links Funding (Transport Scotland Grant Fund)  - Elgin High Cycle track Birnie Crescent to Springfield - £238,250.00

2017/18

Cycling Walking Safer Streets (Transport Scotland Grant Fund) – Reiket Lane Elgin, Cycle Path Extension - £49,847.00 Cycling Walking Safer Streets Fund (Transport Scotland Grant Fund) – A942 High Street Buckie, New Traffic Signals – Cost for cycling related contribution - £10,168.81 Elgin Traffic Management (Capital Fund) – A941 Hay Street Elgin Signals Phase 1 - Cost for cycling related contribution - £5,000.00

2018/19

Cycling Walking Safer Streets (Transport Scotland Grant Fund) – Reiket Lane Elgin, Cycle Path Extension - £3,711.00 Cycling Walking Safer Streets (Transport Scotland Grant Fund)  – Lossiemouth Cycle track, Link to Kinnedar Steading - £2,293.73 Low Carbon Travel and Transport (European Grant Fund)  – Upgrade works to Speyside Way - £27,535.00

2019/20

Low Carbon Travel and Transport Fund (European Grant Fund)   – Upgrade works to Speyside Way - £329,358.05
Developer Funding – Springfield Pinefield Cycle track - £103,313.78 Road Safety Fund (Capital Fund) - A941 School Brae Lossiemouth Signals - Cost for cycling related contribution still TBC, in accordance with section 17 of the Freedom of Information (Scotland) Act 2002 please be advised that this information is therefore not held. 

3. and 4. We have not constructed any dedicated segregated cycling infrastructure in the last 5 years, so no further information to give.

Rate this Page